The contract consisted of the following major works:
Earthworks (excavations): 21 000 m3;
Strengthening shoulders with crushed stone: 31 500 m2
Pavement works consisted the following major works:
– Black crushed stone (crushed stone coated with bitumen), h= 10cm – 7 000 Tn.
– Base course made of course porous asphalt concrete h= 6cm – 23 600 Tn.
– Wearing course asphalt concrete h= 4cm. – 20 000 Tn.
– Base course made of crushed stone h=30cm – 19 500 m3.
– Layer of ballast, h=15cm – 10 000 m3
Construction of culverts – 7 units
Repair of concrete bridges – 4 units
(Bridge km 54+088; km 58+916; km 66+095; km 61+280.)
Installation of crash barriers – 13 000 m
Road marking – 9 900 m2